Advertisement
Update on planning application for former TBA Site
Date published: 28/11/2005
Rochdale Council Planning and Regulation Services have had a number of enquiries regarding progress on the work being undertaken by consultants advising the Council on the land contamination issues relating to the site.
Background
On receiving the planning application in December 2004, the Council sought expressions of interest from appropriate consultants to assist them review the information and proposals relating to land contamination, and related health concerns arising from the application.
In February 2005, we selected Atkins Global to review both the information submitted by the applicant and to assess what further information is needed to decide if the proposals can be carried out safely. The consultants advised that the work was best split into two distinct reports; one for asbestos issues and one for other contaminants. The work on these reports began in April 2005.
Both reports will advise on what further investigation work is required and set out the issues that any remediation scheme must address. The asbestos report will also give comment on sampling accuracy and techniques employed by the applicants and what further work needs to be undertaken. The consultants have had access to all the information supplied by the applicant and held by the Council and they have obtained information independently from local people.
Ken Smith, Head of Planning and Regulation Services said. "It had been anticipated we would have had the report by now, but the consultants undertook some further work, which led to some delay. Additionally, they have advised that they consider their conclusions regarding the asbestos contamination issue should be reviewed by specialists, The Institute of Occupational Medicine, before the final report is sent out to us. We are expecting this to be completed in late December or January."
When the report is received the service will notify all interested parties as soon as officers have had time to assess the work, to ensure that the consultants have fulfilled the Council's brief, that is, that the report covers the issues they were to address.
Ken Smith added. "It is not envisaged that the report will provide all the answers. It will hopefully lead us into the next stage of the planning process - to advise the applicant companies what further investigation work they need to do, and what further information we require regarding the contamination of the site and its remediation, in order for the application to be progressed.
This will be in addition to other matters not relating to contamination, which have already been raised with the applicants, which require further information and/or amendments to the submitted application."
When the service has received all further information the application will be re-publicised.
It is likely that following receipt of further information from the applicants relating to contamination, the service would be looking for its consultants to assess this.
Ken Smith concluded. "I would like to emphasise that only when, and if, we are fully satisfied that all contamination issues have been properly and satisfactorily addressed, and that the proposals are acceptable in planning terms, would we go to the Planning Sub-Committee with a recommendation to grant permission. We anticipate this will not be for quite a while."
Have Your Say


Post New Comment
To post a comment you must first Log in. Don't have an account? Register Now!